Integrated Gas Treatment Plant

client-globe
Location:

Pokrovka Field, Orenburg Region

TDE was awarded a contract to supply the EPFCM of an integrated gas treatment plant with a nominal inlet gas flow of 450,000,000 m3/year @ 0.12-0.25 MPag and 10°C.

The project included detailed design (process, mechanical, electrical, instrumentation, and control) and fabrication of the gas treatment plant. TDE conducted shop testing of all equipment and systems prior to shipping and supplied spare parts for commissioning, start-up, and two years of operation, as well as plant chemicals, lubricants, and firefighting equipment.

The plant was registered with Russian authorities (GOST-R and Permit to Use). TDE was also responsible for construction management, commissioning, start-up, the operational performance test, and personnel training for processes and operation, with emphasis on an automated control system with local and remote monitoring stations. TDE managed transportation to the site for the entire project on behalf of the client.